Any information for the Rt. 422 Road Construction project that is directed for community awareness will be posted on this page of the website until the project is completed. The most recent will be near the top of the page while older alerts will be closer to the bottom. This service was part of an agreement from the trustees and those working on the project to help promote communications to Parkman Residents. Thank you for your support to our website as a choice to get notices out to you. - Cory Anderson
November 27th, 2008
GEAUGA COUNTY
*UPDATED*U.S. 422 (Main Market Rd.) Reconstruction, Parkman and Nelson Townships
Crews have reopened westbound U.S. 422 to traffic. Detours are no longer in
effect. Minor operations, including landscaping, will continue into the spring
of 2009. Only minor impacts to traffic are expected. The entire project
reconstructs U.S. 422 to include four driving lanes and a center turn lane
between SR 88/528 and the Portage County line. Tentative completion date: May
2009.
November 25th, 2008
GEAUGA COUNTY *UPDATED* U.S. 422 (Main
Market Rd.) Reconstruction, Parkman and Nelson Townships
Paving is complete, only minor operations remain. Crews hope to reopen westbound
U.S. 422 on or around November 25, weather permitting. Westbound traffic remains
detoured via SR 5 to SR 82 to SR 44. Eastbound traffic is maintained. The entire
project reconstructs U.S. 422 to include four driving lanes and a center turn
lane between SR 88/528 and the Portage County line. Minor operations, including
landscaping, will continue into the spring of 2009. Only minor impacts to
traffic are expected. Tentative completion date: May 2009.
November 6th, 2008
GEAUGA COUNTY *UPDATED* U.S. 422 (Main Market Rd.)
Reconstruction, Parkman and Nelson Townships
Paving is complete, only minor operations remain. Crews hope to reopen westbound
U.S. 422 on or around Friday, November 14, weather permitting. Westbound traffic
remains detoured via SR 5 to SR 82 to SR 44. Eastbound traffic is maintained.
The entire project reconstructs U.S. 422 to include four driving lanes and a
center turn lane between SR 88/528 and the Portage County line. Minor
operations, including landscaping, will continue into the spring of 2009. Only
minor impacts to traffic are expected. Tentative completion date: May 2009.
Please exercise caution in work zones. For statewide construction information
visit:
www.buckeyetraffic.org
September 18th, 2008
GEAUGA COUNTY
*UPDATED*U.S. 422 (Main Market Rd.) Reconstruction, Parkman and Nelson Townships
Crews continue pouring the last segment of the retaining wall. The structure is
expected to be complete during the week of September 22. Concrete pouring has
begun starting in the center turn lane and working outward. Westbound traffic is
detoured via SR 5 to SR 82 to SR 44 and will be detoured for the duration of the
project, eastbound traffic is maintained. The entire project reconstructs U.S.
422 to include four driving lanes and a center turn lane between SR 88/528 and
the Portage County line. Tentative completion date: November 2008.
August 21st, 2008
GEAUGA COUNTY
*UPDATED*U.S. 422 (Main Market Rd.) Reconstruction, Parkman and Nelson Townships
Crews are currently preparing for concrete pavement by fine-grading the concrete
sub-base. Crews have resumed work on the retaining wall. Bridges work is
essentially complete. Placement of the center turn lane throughout the project
limits will begin during the coming weeks. Westbound traffic is detoured via SR
5 to SR 82 to SR 44 and will be detoured for the duration of the project,
eastbound traffic is maintained. The entire project reconstructs U.S. 422 to
include four driving lanes and a center turn lane between SR 88/528 and the
Portage County line. Tentative completion date: November 2008.
August 19th, 2008
To: Main Market Rd. Resident
Re: Driveway access, upcoming work
Dear Sir or Madam,
For residents at:
#16640, 16642, 16644,16654,16680,16710,16730,16772,16776,16790,16824
Please be advised that as of Monday, August 25th, 2008, the entrance to your driveway will be maintained through the ramped entrance behind the barrier wall located at the West end of the project. From this entrance you will travel East on the compacted base material toward your residence.
When exiting your driveway, you should still travel Eastbound (left turn out of your residence) and exit onto the live traffic lane at the ramp up onto the new pavement located before the bridge over the Grand River.
For residents at: 17000, 17086, 17108
When paving work begins on August 25th, enter your residence through the ramp located at 17000 Main Market Rd. (River Pines Main Entrance) and travel East to your driveway. When exiting, travel East to the ramp at the end of the project and merge into Eastbound traffic at that median crossover.
Thank you for your attention to this matter. Should any additional information be required, do not hesitate to contact us at (330.903.1108).
Sincerely,
Karvo Paving Company
August 1st, 2008
GEAUGA COUNTY *UPDATED*U.S. 422 (Main Market Rd.)
Reconstruction, Parkman and Nelson Townships Work to remove
the westbound lanes between SR 282 and the Portage County line is complete and
crews currently work to cement stabilize this portion of roadway. Concrete deck
and approach placement is complete on the bridges over the Grand River and a
tributary of the Grand River. Westbound traffic is detoured via SR 5 to SR 82 to
SR 44 and will be detoured for the duration of the project, eastbound traffic is
maintained. The entire project reconstructs U.S. 422 to include four driving
lanes and a center turn lane between SR 88/528 and the Portage County line.
Tentative completion date: November 2008.
July 24th, 2008
GEAUGA COUNTY
*UPDATED*U.S. 422 (Main Market Rd.) Reconstruction, Parkman and Nelson Townships
Work to remove the westbound lanes between SR 282 and the Portage County line is
complete and crews currently work to cement stabilize this portion of roadway.
Concrete deck and approach placement is complete on the bridges over the Grand
River and a tributary of the Grand River. Westbound traffic is detoured via SR 5
to SR 82 to SR 44 and will be detoured for the duration of the project,
eastbound traffic is maintained. The entire project reconstructs U.S. 422 to
include four driving lanes and a center turn lane between SR 88/528 and the
Portage County line. Tentative completion date: November 2008.
May 8th, 2008
Public Notice - Reynolds Road is now closed to all thru traffic until further notice. Karvo began earthwork near Reynolds Rd. on Monday, April 28th. Depending on weather, daily progress, etc., the closure will be for several months.. Detour signage has been posted that is detailed in ODOT’s maintenance of traffic plan which detours traffic around this road demolition. Thank you for your patience.
February
22nd, 2008
To: Main Market Rd./Parkman Rd. Resident
Re: Traffic
Pattern Shift 02/25/08
Dear Sir or Madam,
Regarding Karvo/ODOT’s
instructions for affected residents on the topic of driveway access, please read
the following:
The traffic switch is
now scheduled for Monday February 25th,2008. Be advised that
once the one lane of East bound traffic is moved onto the new pavement, work on
the demolition of the remains of the two bridges within project limits and storm
drainage construction will begin soon afterward. This means that driving
within the work area (which is illegal to begin with) will be extremely
treacherous. ALL residents are advised to use only approved entrance and
exit locations from the work zone or their homes at all times. These
locations are:
For Phase 2
beginning immediately after traffic is flipped:
South
side Residents-Traffic
pattern will be similar to permanent, with the only difference being traffic
will be confined to the outside (southern most) lane. NO WESTBOUND TRAFFIC
ALLOWED, FOLLOW ODOT DETOUR.
North
side Residents-Exit
and enter driveway by crossing the unpaved area that is the future turn lane by
using the paved aprons directly across from each driveway. When exiting a
residence, turn left, then merge into EASTBOUND traffic only. When entering from
the West, turn off the new pavement and use the same temporary aprons. NO
WESTBOUND TRAFFIC ALLOWED, FOLLOW ODOT DETOUR.
Sincerely,
Karvo
Paving
February
14th, 2008
To: Main Market Rd./Parkman Rd. Resident
Re: Driveway
access in SR422 Construction Zone
Dear Sir or Madam,
Regarding Karvo/ODOT’s
instructions for affected residents on the topic of driveway access, please read
the following:
The traffic switch is
now tentatively scheduled for late February. Be advised that once the one
lane of Eastbound traffic is moved onto the new pavement, work on the demolition
of the remains of the two bridges within project limits and storm drainage
construction will begin soon afterward. This means that driving within the
work area (which is illegal to begin with) will be extremely treacherous.
ALL residents are advised to use only approved entrance and exit locations from
the work zone or their homes at all times. These locations are:
For Phase 2
beginning immediately after traffic is flipped:
South
side Residents-Traffic
pattern will be similar to permanent, with the only difference being traffic
will be confined to the outside (southern most) lane. NO WESTBOUND TRAFFIC
ALLOWED, FOLLOW ODOT DETOUR.
North
side Residents-Exit
and enter driveway by crossing the unpaved area that is the future turn lane by
using the paved aprons directly across from each driveway. When exiting a
residence, turn left and merge into EASTBOUND traffic only. When entering from
the West, turn off the new pavement and use the same temporary aprons. NO
WESTBOUND TRAFFIC ALLOWED, FOLLOW ODOT DETOUR.
Sincerely,
Progress Meeting for the U.S. 422
Construction Project: Tuesday 1/08/08.
Present:
Pete & Al from The Cleveland Group; Guido from Karvo Paving; Ron, Randy, and Tom from ODOT; Pat Joyce from Parkman Township.
Important information from meeting pertaining to Parkman residents: